الإدارة والاقتصاد الهندسي
A project costs SAR 80,000 and yields SAR 25,000 per year for 5 years plus SAR 10,000 salvage at year 5. At 12%, its NPV is closest to:
اعرض الإجابة والشرح
الإجابة الصحيحة: C SAR 15,794
PW الدخل = 25,000 × 3.6048 = 90,119، PW الخردة = 10,000 × 0.5674 = 5,674. NPV = −80,000 + 90,119 + 5,674 ≈ 15,794.